Construction Schedule

Here is the construction schedule for the UpGarden -- updated 5/9/2012

View/Download a PDF version (the pdf version contains additional information about the people involved and estimated volunteer hours needed).

Construction Sequence   MAY   JUNE
Item Date Sat 5/5 & following week Sat 5/12 & following week Sat 5/19 & Following week Sat 5/26 Sat 6/2 OPENING CELEB.
Project Start-Up            
Close down garden area COMPLETE          
Erect temporary vehicle barriers if needed COMPLETE          
Garden Prep            
Powerwash garden area COMPLETE          
Prep Airstream to be placed outside and be secure COMPLETE          
Art Car Planter (Prep and Move Tow in) ONGOING          
Bed and Path Layout COMPLETE          
Move in Airstream COMPLETE          
Remove concrete curb at West end of garden COMPLETE          
Provide Irrigation point of connection COMPLETE          
Garden Construction Phase I (Core
Infrastructure)
           
Terraces: Construct support posts for garden terraces (including trellis posts) 4/25-5/16 (approx) work planned        
Terraces: Attach facing of terraces and
terrace cap & Construct terrace sidewalls
approx. 4/25 - 5/20 work planned work planned work planned    
Construct raised beds approx. 4/25 - 5/20 work planned work planned work planned    
Install irrigation mainlines and hosebibs   work planned work planned      
Paint pavement mural            
Blow in soil         work planned  
Blow in and move woodchips         work planned  
             
Garden Construction Phase II (Making it
functional)
           
Improve Toolshed (Ramp, etc.)   work planned work planned work planned work planned  
Construct trellises            
Complete irrigation system       work planned work planned work planned
Seed/ Sod grass gathering area         work planned  
Construct benches         work planned  
CELEBRATION PARTY! 2-Jun         work planned
Construct Compost Bins            
String out garden plots            
Construct Gates            
             
Garden Construction Phase III (Making it
fun)
           
Construct/Install Kiosk            
Bring in tables, chairs, etc.            
Build Bee Enclosure and Bee Hive            
Build Bird Houses            
Plant Herbs, pollinators, fruit trees,
etc.
           
Paint terrace stencil            

Share Us to your Page On...

Twitter icon
Facebook icon
Google icon
StumbleUpon icon
Del.icio.us icon
Digg icon
LinkedIn icon
MySpace icon
Newsvine icon
Reddit icon
Technorati icon
Yahoo! icon
e-mail icon